Representative cases:
• Successfully defended prime contractor in connection with $26 million claim for alleged design, product and construction failures in construction of waste water treatment facility;
• Successfully represented specialty carpentry contractor in delay and impact claim on large school construction project;
• Successfully represented supplier in action involving $1 million alleged product failure on multi-million dollar rehabilitation project for public water authority;
• Successfully represented owner/developer in the defense of change order, delay and other impact claims submitted by design build prime contractor and prosecution of related change order and liquidated damage claims against design builder on $20million+ project for construction of independent and assisted living facility;
• Successfully represented specialty masonry contractor in delay and impact claim on public school construction project;
• Represented surety in litigation and mediated settlement of alleged default and termination of electrical prime contractor on public school construction project;
• Successfully represented prime contractor in unforeseen site condition and related delay/impact claim involving construction of upgrades to water/waste water treatment facility;
• Successfully represented site work prime contractor in connection with change order and back charge claims on residential subdivision project; and
• Successfully represented prime contractor in change order claims and owner declared default on municipal building/public library construction project.
• Successfully represented surety in claimed performance bond default and multiple related payment bond claims on Philadelphia municipal project, arranging for completion of the Project